Updated  08/29/06

Intracoastal Waterway, Miami-Dade County – Phase I

Summary of Work Performed

 

August 2000

 

            We have essentially completed Task I-A (Data Collection) and Task I-C (Establishment of Long-Term Requirements), based on all information presently available.  Specifically, we have reviewed all available sediment chemistry data for the Dade County project area (Task I-C.1), including data recently obtained by the Jacksonville District, U.S. Army Corps of Engineers’ (COE) in their recent comprehensive channel sediment survey. However, additional COE core boring logs and grain-size data expected from the same sediment survey, although included in the same contract, was not obtained and will not be available to assist in the present planning effort.  Absent this data, we selected appropriate sediment sampling locations for our planned sampling program, scheduled for the week of September 11th.  We compiled and reviewed all available Jacksonville District, U.S. Army Corps of Engineers’ (COE) archival dredging records and channel surveys and projected a preliminary estimate of future dredging and material storage requirements (Task I-C.2) for the 10-ft project segment within Dade County. We completed our analysis of the final data set from the Jacksonville District’s three line survey of the entire ICWW, including the Dade County segment south to the Monroe County line and, based on the results of this survey, updated our preliminary projections for the 10-ft project segment and extended our projections to encompass the 7-ft project segment as well.  We have inventoried all existing easements within the project area based on our review of relevant COE Real Estate maps and Control Data sheets for the Intracoastal Waterway, Jacksonville to Miami and Miami to Key West (Cross Bank), and 1994 FIND blueline aerials, evaluated these easements with respect to their potential material storage capacity (Task I-C.3), and calculated the project area’s existing material storage capacity (Task I-C.4). However, given the concentration of existing shoaling around Baker’s Haulover Inlet and the potential for beach placement of appropriate channel sediment in this area, final definition of operational channel reaches must wait until we receive the data from our sediment sampling program to delineate the channel segment containing beach quality material, as well as to characterize sediment conditions throughout the 7-ft project segment for which no reliable data is presently available.

 

            The results of Task I allowed the preliminary evaluation of likely material management concepts (Task II-A) and the identification of 63 additional candidate sites (Task II-C) based on an office review of 1994 NAPP color-IR aerial photography, USGS 7.5-minute topographic quadrangle maps, Comprehensive Plan Future Land Use maps and U.S. Department of the Interior wetland inventory maps.  We are proceeding with the evaluation of these candidate sites (Task IV). To update each candidate site’s present land use, we obtained current (1999) Dade County tax aerials for all candidate sites.  Through review of these aerials, we eliminated 11 candidate sites with obvious land use conflicts (i.e., recent development) not shown in the 1994 aerials, and thereby reduced the number of required candidate site inspections.  During the weeks of April 10th and April 24th, a engineer-biologist team inspected all remaining candidate sites as well as the two existing sites with some potential for continued use (Task III).  We are now completing the mapping of land use and vegetation communities on each site to Level 3 of the Florida Land-Use and Cover and Forms Classification System (FLUCS) (FDOT, 1985), based on the 1999 Dade County aerials and proceeding with each site’s evaluation (Task IV) under the full standard set of engineering, operational, environmental, socioeconomic, and land-use criteria. We have thus far received over 40 candidate site maps from our biological and mapping subcontractor and are now drafting site data summary sheets and narratives for these sites. We are now preparing all materials to present the results of Task IV at the next round of Technical and Citizens’ Advisory Committee meetings/public workshops in November.


            Following up on an earlier meeting, Taylor Engineering staff met on August 21st with Susan Markley of the Metro-Dade Department of Environmental Resources Management (DERM) to review the earlier discussion on our present list of candidate sites and recommendations for additional candidate sites.  Following this brief meeting, Taylor Engineering staff made initial visits to several potential sites along the Miami River, revisited the three candidate sites on Virginia Key, and located several abandoned former powerboat manufacturing sites in an area known as Thunder Alley, just west of Dumbfoundling Bay.  We are now preparing to formally inspect these sites with an engineer-biologist team, as well as at least three additional sites east and southeast of the former Homestead Air Force Base suggested by DERM.