Updated
10/13/06
Progress Report
Tasks I through III
Phase I Long Range Dredged
Material Management Plan
for the Intracoastal
Waterway
in Miami-Dade County
May 24, 2000
This report summarizes the results of our work on Tasks I
through III for the Phase I development of the Long Range Dredged Material
Management Plan for the Intracoastal Waterway (ICWW) in Miami-Dade County, Florida
(Figure 1). Specific efforts expended in the completion of these tasks, as well
as results obtained from these efforts, will be reported to the project’s
Technical Advisory Committee on May 24th, the project’s Citizens’
Advisory Committee on May 30th, the general public on June 6th,
and the FIND Board of Commissioners on June 23rd at their regularly
scheduled meeting in Brevard County.
Review of Resource Materials
The attached tables and figures summarize the results of
Tasks I through III. Task I results
reflect the analysis of information from materials collected during project
Task I-A (data collection). These materials include U. S. Geological Survey
(USGS) NAPP 1994 color-infrared aerials, USGS 7.5-minute series topographic
quadrangle maps, and U. S. Fish and Wildlife Service National Wetland Inventory
maps (all at a scale of 1:24,000) of the entire project area, 1994 Florida
Inland Navigation District (FIND) blueline aerials of the 10-ft project segment
of the Waterway, showing existing disposal easements and FIND-owned properties
(1:2,400), Jacksonville District Corps of Engineers Real Estate and Control
Data maps, 1999 Miami-Dade County Tax Assessment aerials (scale 1:3,600), and Miami-Dade
County Comprehensive Plan future land use elements and maps. As part of this
task, we have reviewed all relevant dredging records (plan documents, surveys,
dredging summaries, OCE reports, etc.) held by the Jacksonville District Corps
of Engineers (COE). We also have analyzed the comprehensive survey data from
the FIND’s 1996 survey of the entire 10- and 12-ft project segments of the ICWW
channel including the 10-ft project segment within Miami-Dade County. Notably, this
survey did not include the ICWW channel from Government Cut southward to the Miami-Dade\Monroe County line. We have just recently (April 21st) received
data from the Jacksonville District’s recent survey of the entire ICWW channel,
including data from Government Cut southward, and are now beginning its
analysis. Finally, we have reviewed all available sediment data and reports
from the Florida Department of Environmental Protection and South Florida Water
Management District characterizing the chemistry of the Waterway sediments. We
have also reviewed sediment chemistry data obtained as part of a recent
Jacksonville District COE program to characterized channel sediment throughout
the ICWW in Florida. However, we still await core boring logs and sediment
grain-size data from that same COE program before we determine the most
appropriate channel locations in which to concentrate our planned sediment
sampling, not yet scheduled.
Project Definition
The Miami-Dade County segment of the ICWW extends approximately
48 miles from the Broward/Miami-Dade County line between Hallandale and Aventura
southward to the Miami-Dade/Monroe County line in Card Sound south of Biscayne Bay.
Portions of two separately-authorized federal navigation projects — the 10-ft
Project (Ft. Pierce to Miami) and the 7-ft Project (Miami to Key West) comprise
the Intracoastal Waterway within Miami-Dade County. The 10-ft Project (Ft. Pierce to
Miami) extends southward to the Port of Miami Channel (Government Cut) and
includes authorized dimensions of 10 ft below Mean Low Water (-10 ft MLW) depth and 125 ft base channel
width. The 7-ft Project (Miami to Key West) extends southward from Government
Cut and within Miami-Dade County includes authorized dimensions of -7 ft MLW depth and 75 ft base channel
width. For the present planning effort, the Miami-Dade County project area extends
47.92 miles from a point approximately 530 ft south of the Broward\Miami-Dade County
line (ICWW mile 333.24; Cut DA-1, Station 0+00) to the Miami-Dade/Monroe County
line
(Figure 1). The county’s northernmost 530 ft lie within the southernmost
Broward County cut (Cut BW-63) and are addressed as part of the long-range plan
for the ICWW in Broward County.
To provide a project framework,
Table 1 lists all of the Miami-Dade County channel cuts (i.e., the straight line channel segments) within the
10-ft Project, across the Port of Miami turning basin, and within the 7-ft
Project; the length of each cut; and the corresponding mileages measured from
three starting points: the northern boundary of the Miami-Dade County project area,
the northern end of the Intracoastal Waterway at the St. Johns River in
Jacksonville (specifically, the southern edge of the Jacksonville Harbor
Project, designated ICWW mile 0.0), and the northern end of the Atlantic
Intracoastal Waterway within Florida near the Florida/Georgia border
(specifically, the southern edge of the Fernandina Harbor Project, designated
AIWW mile 0.0).
Projected Dredging and Material Storage Requirements
To project future dredging and material storage
requirements for the Miami-Dade County project area, we first compiled and reviewed
all available Jacksonville District, U.S. Army Corps of Engineers’ (COE)
archival dredging records and channel surveys, as stated above. By this
process, we determined that within the 10-ft Project segment, eight separate
maintenance dredging operations have been performed since this segment of the
channel was deepened to its presently authorized depth in 1965. As shown in
Table 2, all took place within a 0.5-mile reach extending from ICWW mile 339.26
(Cut DA-9, sta 22+00) to ICWW mile 339.75 (Cut DA-9, sta 48+00) immediately
opposite Baker’s Haulover. These eight operations removed a total volume of
over 323,000 cubic yards (cy), or an average of over 40,000 cy per operation.
The FIND’s December 1996 three line survey of the entire ICWW south to
Government Cut, and the only recent comprehensive survey of the Miami-Dade County
10-ft Project segment, documented an additional 12,400 cy of shoaling found
primarily in a 1.2-mile reach centered about the 79th Street
Causeway (ICWW mile 343.12 to mile 344.28). From these data, we then projected
for the 10-ft project segment within Miami-Dade County a 50-year dredging requirement
of 508,230 cy, and a 50-year projected material storage requirement of
1,092,6954 cy, based on an assumed bulking plus overdredging factor of 2.15.
Notably, 96% of this projected requirement reflects shoaling immediately
opposite Baker’s Haulover. Although sufficient to guide our initial
identification and evaluation of candidate sites, this projected material storage
requirement will be refined based on the results of the Jacksonville District’s
recently completed three line survey of the entire ICWW, including the Miami-Dade
County segment.
The Jacksonville District’s archives contain little
information about historic dredging within the Intracoastal Waterway southward
from Government Cut (i.e., within the Intracoastal Waterway 7-ft Project, Miami
to Key West). The records indicate that the authorized channel was constructed
to Cross Bank near Plantation Key in Monroe County, but do not specify when the
dredging took place. Examination of nautical charts (the only presently
available source of bathymetric information within this segment of the Miami-Dade
County project area) suggests that construction of this portion of the project
required only minimal dredging through a limited number of shoals, or banks.
The remainder of the authorized channel appears to have been naturally at or
below the 7-ft project depth. No record of maintenance dredging since the
channel’s original construction was found. Ongoing analysis of data recently
received from the Jacksonville District will provide the only available
comprehensive update of the channel’s condition and will form the basis from
which to project present and future dredging and material storage requirement (Figure
2).
We also inventoried all existing disposal easements
within the Miami-Dade County project area, based on review of relevant COE Real
Estate maps and Control Data sheets for the Intracoastal Waterway, Jacksonville
to Miami (10-ft Project), FIND Maps of Proposed Right-of-Way and Maintenance
Spoil Areas along the Intracoastal Waterway from the Dodge Island Seaport
southerly to the Miami-Dade-Monroe County Line in Miami-Dade County (1970), and 1994
FIND blueline aerials We then derived preliminary estimates of site parameters
(e.g., upland acreage, capacity, pipeline access, etc.) from the above
described resource materials. A complete inventory of all existing easements
and the results of the preliminary easement evaluation process are summarized
in Table 3 and Figure
3. By this process, we determined that only two existing
easements — a portion of Sandspur
Island opposite Baker’s Haulover and a portion of Legion Picnic Island Park
south of the 79th St. Causeway — possess any realistic potential for
development as dredged material management areas and thus merit further
evaluation. Notably, these two sites are located near the two documented shoal
areas. However, the total storage
capacity of these two properties, estimated as over 72,000 cy, represent less
than 7% of the projected 50-year storage requirement of the 10-ft Project
segment within Miami-Dade County. Moreover, use of these sites may not represent the
most cost-effective or operationally efficient means of meeting these long-term
needs of the Waterway within Miami-Dade County. We are now refining these preliminary
estimates of useable site acreage and potential site capacity within these two
sites based on field inspections and detailed site mapping as discussed below.
Dredged Material Management Concepts
Based on the results of Task I and review of the overall
physical, environmental, and demographic characteristics of the coastal areas
of the county, we then preliminarily identified the most appropriate material
management strategy for the requirements of 10-ft Project segment of the Miami-Dade
County project area. Given the concentration of shoaling around Baker’s
Haulover, and the likely presence of beach-quality channel sediments in this
segment of the Waterway, beach placement, supplemented by an nearby upland
staging and material transfer area, appears to be the most appropriate
management strategy for this channel segment. However, the presence of
beach-quality channel sediment must be demonstrated by sediment data soon to be
to be received from the Jacksonville District COE, and confirmed by additional
sediment sampling based on this data. For the remainder of the 10-ft Project
segment, the use of confined upland placement in a limited number of
centralized material management areas appears the most appropriate material
management strategy.
The environmental sensitivity and protected status of much
the area through which the 7-ft Project
Candidate Site Identification and Field Inspection
Although not yet final, the results of Task I and the
preliminary definition of appropriate management concepts for the 10-ft Project
segment of the Miami-Dade County project area then guided the identification of 63
additional candidate sites based on an office review of 1994 NAPP color-IR
aerial photography, USGS 7.5-minute topographic quadrangle maps, Comprehensive
Plan Future Land Use maps and U.S. Department of the Interior wetland inventory
maps. To update each candidate site’s present land use, we then obtained
current (1999) Miami-Dade County tax aerials for each area identified. Through review
of these aerials, we eliminated 11 candidate sites with obvious land use
conflicts (i.e., recent development) not shown in the 1994 aerials, and thereby
reduced the number of required candidate site inspections. Field inspection of
the remaining candidate sites (Figure 4-1, Figure
4-2 and Table 4), as well as the two
existing sites that show some potential for development as dredged material
management areas, was conducted the weeks of April 10th and April 24th.
A team consisting of one engineer and one biologist inspected each existing and
newly-identified candidate site not presently available to the FIND to
determine existing land uses on and adjacent to each site, to characterize and
preliminarily quantify on-site vegetation communities and associated
environmental liabilities, and to assess the general suitability of each site
for development as permanent dredged material management facilities.
In Task IV, each candidate site will
be further evaluated under the full standard set of engineering, operational,
environmental, socioeconomic, and land-use criteria. We are now mapping land
use and vegetation communities on each site to Level 3 of the Florida Land-Use
and Cover and Forms Classification System (FLUCS) (FDOT, 1985), based on the
1999 Miami-Dade County aerials. When completed, these maps will guide a refined
estimate of each site’s dredged material storage capacity, based on realistic
containment basin geometries, field-verified environmental constraints, and
appropriate setback considerations. The
resulting site capacities, acreage requirements, and basin geometries, as well
as each site’s associated reach requirements and land-use parameters, will be
outlined in a Site Data Summary Sheet to accompanying each candidate site map.